EDIC/Lynn
Economic Development & Industrial Corporation of Lynn, Massachusetts
 
       

Power line project to cost Lynn around $4.5M, 2 1/2 years to complete

August 9, 2007
By Robin Kaminski/The Daily Item

The cost to relocate transmission lines off of the Lynn Harbor waterfront, excluding land rights, will cost roughly $4.5 million to complete, according to the Lynn Harbor Line Relocation Study by Vanderweil Engineers,

The estimate, which has not yet gone out to contractors for review and bid, is based upon current market conditions and is higher than previous estimates due to construction costs and materials.

State funds were recently awarded to the city totaling $2.5 million to assist in the process, with the remaining costs paid for by stakeholders according to Councilor at Large Paul Crowley.

"I'm very optimistic that the deal can be worked out with General Electric within the next three months," he said. "Discussions have been ongoing and I understand that they may be looking for something in return, along the lines of changes to tax laws that would be favorable to them. However, it shouldn't be of any cost to the city."

Crowley, who said he has been working on the issue for the past two years with Ward 6 Councilor Peter Capano, said relocating the power lines is a major piece of the puzzle.

"There was talk initially of burying the power lines underground, but the cost would be just too great," he said. "In 30 years, someone might say that they need to develop around the GE site and that the power lines are now in their way...but that's an issue for another day."

Approximately 24 towers would be relocated within roughly one mile of transmission lines that lie in between the General Edwards Bridge and the sewage treatment plant. New double circuit transmission towers would be installed in their place.

"The timing is actually pretty good for this project, because the power lines were set to receive an upgrade in the near future anyway," Capano said. "So this would save money along the way as well."

According to the study, once the project is approved, it's expected to take approximately 2.5 years to complete the relocation, based upon a four month engineering study, 12 months to complete licensing requirements, eight months for material acquisition and six months for construction.

An environmental assessment completed by Vanasse Hangen Brustlin, Inc. (VHB) assessed the environmental, permitting, licensing and land rights required to move the project forward.

While the study found there were no rare or endangered species located within the transmission lines, VHB determined that a soil management plan needs to be completed to address areas of suspected contamination.

 

Back to News

 

Economic Development & Industrial Corporation
Lynn City Hall ~ Room 307  .  3 City Hall Square, Lynn MA 01901
Phone: 781.581.9399  .  Fax: 781.581.9731  . 
Email: info@ediclynn.org